About us

We work with you to solve your energy challenges through innovative solutions, delivering resilience, cost efficiency and sustainability

About us overview
Power crew’s flying visit lifts museum
Power crew’s flying visit lifts museum

14 June 2022: Fifty staff from UK Power Networks Services donated their time to a speedy makeover of the memorial garden, outdoor seating areas, visitor pathway and service courtyard of the Army Flying Museum in Hampshire.

Read more

Sustainability

Enabling Port of Felixstowe to take major step  towards Net Zero
Enabling Port of Felixstowe to take major step towards Net Zero

6 June 2022: UK Power Networks Services has won a contract to take the UK’s largest container port, and one of the largest in Europe, a step closer to Net Zero.

Read more

Industries

Our clients include some of the highest profile public and private sector organisations with critical infrastructure in complex environments.

Our industries
High Speed 1
High Speed 1

We were commissioned to design, construct, operate and maintain the electrical infrastructure of HS1, the UK’s first major railway constructed in over a century and its first high-speed railway. The project was delivered on time and on budget, within a contract that extends for 50 years after the start of railway operation.

Read more

Kent Power Supply Enhancement

Gettyimages 520735682 Website

We upgraded the electricity infrastructure on the north and mid-Kent lines to meet the Train Operating Company’s aspiration to run 12-car trains, increasing capacity by 20%.

Background

The project addresses the requirement to upgrade the E&P infrastructure on the north and mid-Kent lines to meet the Train Operating Company’s (TOC’s) aspiration to run 12-car trains, increasing capacity by 20% from the current 10-car units.

Phase 1 enhances the infrastructure to cope with a limited number of 12-car Class 465 units on the lines between London and Gravesend, London and Hayes, and London and Sevenoaks. The works are designed to achieve a 7.5kA route setting.

 

Scope

To provide a 7.5kA route setting and a traction voltage uplift to 750V DC third rail, covering the refurbishment and upgrading of twenty two substations and Traction Paralleling Huts (TPHs) and forty eight Electrical Track Equipment (ETEs). This required around 70km of cable and many associated other electrical works, operating on a short timescale at over seventy sites.

 

Substations and Traction Paralleling Huts (TPHs)

  • 33kV switchgear – three panel HVCB suite
  • Transformer rectifiers – 3MW Class G
  • 750V switchgear – switchgear resistor change, 4kA DCCBs, 6kA Main DC and cables to rectifier; 8kA Main DC and cables to rectifier
  • Protection equipment – overload changes to new route setting, decommissioning and removal of MITS equipment, increase rectifier protection; impedance protection and frame leakage
  • SCADA – new RTU, update existing RTUs
  • Battery chargers - new TPH, DC switchgear, HV switchgear and rectifier
  • LV equipment – supply to new TPH; 70kVA 33kV. 415V aux. transformer
  • New or diverted LV supply
  • Data and telephone lines – removal, provision, diverted
  • Removal of old equipment
  • New positive (1000mm) (240mm) and negative (800mm) cabling
  • UTX for CMS
  • TPH module base

 

Enhanced ETE

  • Replacement of VIR & VB cables, CAD welded cables and degraded (bubbled) insulation cables

 

Challenges

This very significant programme of works had to be achieved in a very tight timeframe, with over seventy work sites to be surveyed, design and consultation to be carried out, planning secured (Section 61) where needed and agreed works undertaken.

A ‘one team’ approach helped considerably in meeting the fast track pace; facilitated by co-location of Network Rail, UK Power Networks Services and the delivery supply chain at our Chatham office

 

Achievements

  • Rapid mobilisation and set-up of integrated project management office with supply chain
  • TP Hut works started in week three
  • First new DC switchgear commissioned in week ten
  • Track ETE started in week three
All case studies